PROJECT DETAILS

Gaziantep City Steel & PE coated NGPL Project.  Phase No: 5 / Part 6

CLIENT : Gazdas Gaziantep Dogalgaz Dagitim A.S.

PROJECT NAME : Gaziantep City Steel & PE coated NGPL Project. Phase No: 5 / Part 6

TYPE : Pipelines

COMPLETION : 27.05.2011

LOCATION : G. Antep / Turkey

SCOPE

Total 105 km Steel & Polyethylene (PE) Coated Natural Gas Pipeline Construction Project

• Construction of 79.000 meters (ø 40 cm) PE NGPL
• Construction of 20.560 meters (ø 63 cm) PE NGPL
• Construction of 70 metres (ø 90 cm) PE NGPL
• Construction of 3.900 meters (ø 125 cm) PE NGPL
• Installation of 62 pieces (ø 40-63-90-125 cm) Embedded Valve Spools




Project Pictures




« Go Back